10/26/15 Project Update: Parsonage Demolition to Start

The installation of silt fencing and biologs for erosion control around the parsonage will be completed today. Weather permitting, the demolition is scheduled to start on Tuesday, October 27. It should only take a day to tear it down, then crews will spend the rest of the week sorting materials and trucking them out. The bell tower will also be removed during this phase of the project.
 
Once the area is cleared, it will be backfilled and re-graded. Further site development on the east side of the property, such as the addition of a parking lot and landscaping, will not begin until Spring 2016.