01/04/16 Project Update: Sanctuary Addition Work Starting

Here’s a brief overview of what will be happening with our building project during the next few weeks:

  • The section that juts out on the south side of the existing church will be cut loose and demolished, in preparation for the sanctuary addition.
  • Excavation of the sanctuary addition area will be done, followed by pouring of the footings and foundation.
  • The inside area of the kitchen addition will be backfilled in anticipation of pouring the new floor.
  • Inclement weather and the holidays caused delays in the installation of stormwater management tanks. Work resumes this week, and will be followed by grading on the east side of our lot.